How RTC planning Feature Calculate the Progress bar and Load bar in hours


Unknown User (19113) | asked Sep 21 '20, 5:27 a.m.

 In RTC Planning , How we can Calculate the Progress bar and Load bard in hours if i create an iteration from timeline and below would be details of iteartion. Starting Date 18/sep/2020 12:00AM End Date: 23/Sep/2020 12:00AM and i Created a task in same Itearion and Plan at 11:am and Estimated time given 8h what would be the Progress bar calculation and Load bar calculation

One answer



permanent link
Luis Peregrina (18114) | answered Oct 16 '20, 4:40 p.m.
JAZZ DEVELOPER

 https://jazz.net/forum/questions/176753/how-load-is-calculated-at-a-plan > see https://jazz.net/library/article/586

It uses the items planned for that iteration (work done/left) versus user availability (working hours * assigned percentage)