How RTC planning Feature Calculate the Progress bar and Load bar in hours

 In RTC Planning , How we can Calculate the Progress bar and Load bard in hours if i create an iteration from timeline and below would be details of iteartion. Starting Date 18/sep/2020 12:00AM End Date: 23/Sep/2020 12:00AM and i Created a task in same Itearion and Plan at 11:am and Estimated time given 8h what would be the Progress bar calculation and Load bar calculation

0 votes



One answer

Permanent link

 https://jazz.net/forum/questions/176753/how-load-is-calculated-at-a-plan > see https://jazz.net/library/article/586

It uses the items planned for that iteration (work done/left) versus user availability (working hours * assigned percentage)

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 7,495
× 6,121
× 1,325

Question asked: Sep 21 '20, 5:27 a.m.

Question was seen: 1,978 times

Last updated: Oct 16 '20, 4:40 p.m.

Confirmation Cancel Confirm