My standalone 702 server always jumps to life at 3AM and the processor starts thrashing for over an hour and the server becomes difficult to use.

I checked the schedule for DW and all the DW jobs are scheduled to run at 00.00 so it is not DW I don't think.

is there some other scheduled database activity that kicks off at 3AM and can it be changed to a different time?

0 votes


Accepted answer

Permanent link
Normally the DW has two sets of jobs - the core ones at the top run at midnight and the more intensive ones run at 3 from memory.

Check the schedule for the second set of jobs and see if that's it
Sean F selected this answer as the correct answer

0 votes


One other answer

Permanent link

 Hi Sean,


We're on 6.0.6.1, so not sure this applies, but we run this task nightly during the early hours (see RM Advanced Properties)..  Could it be something like that?

com.ibm.team.jfs.indexing.service.internal.CleanUpUnusedIndexesVersionsTask

Carol

1 vote

Comments
Thanks Carol

That is disabled on my server value = -1

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 7,487
× 6,117
× 1,316

Question asked: Apr 02 '21, 12:19 p.m.

Question was seen: 1,668 times

Last updated: Apr 03 '21, 9:59 p.m.

Confirmation Cancel Confirm