I would like the date range of an iteration to be an attribute of a work item.  Does RTC expose this data in any way, shape, or form?

0 votes


Accepted answer

Permanent link
The date range is shown when you hover the mouse pointer over the Planned For attribute.

Technically it is possible to do a lot of things by extending RTC. It would be possible to calculate date attributes, based on the selected iteration, in work item save operations. This would have several problems and disadvantages. E.g. the iteration start and end date could be changed which would not be detected by any work item.
Alexander Reyes selected this answer as the correct answer

1 vote

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,116

Question asked: Mar 31 '20, 5:11 p.m.

Question was seen: 968 times

Last updated: Apr 01 '20, 2:56 a.m.

Confirmation Cancel Confirm