Report for Team Velocity using specific work item type
I would like to adapt the report "Team Velocity" (ready to use) to use a specific work item type only.
The built in version I cannot seem to choose a work item type, but only project area, timeline and team.
So I tried to build a new report but I can't seem to get the sum of the story points...
My questions therefore are:
- can I change the input of the built in Team Velocity report somehow?
or
- can I look at the definition of the built in report?
or
- how can I use the sum of story points of the chosen items for my graph?
Thank you!
|
2 answers
Ralph Schoon (63.5k●3●36●46)
| answered Jun 27 '18, 2:06 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER As far as I can tell, the "Ready to use" reports can not be customized. They use custom sql code that the report builder can not generate.
|
You might try referring to this blog post for building your own custom trend reports, such as a burndown: https://jazz.net/library/article/1562 |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
Assuming Scrum based process templates? RTC version ...?