It's all about the answers!

Ask a question

Can a work item template be incorporated into a project template?


Sean Burke (3789136235) | asked Mar 02 '18, 1:00 p.m.

I have a number of work item templates that I would like to see in any new project area I create.  I would assume those could be made part of project template.  Is this correct?

One answer



permanent link
Matt Muller (59813274) | answered Mar 05 '18, 2:39 a.m.

Sean,

Yes I think you are correct - however watch out for the Planned for and Field Against Values as between projects they probably can't be used.

Regards

Matt

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.