Can a work item template be incorporated into a project template?


Sean Burke (3789144247) | asked Mar 02 '18, 1:00 p.m.

I have a number of work item templates that I would like to see in any new project area I create.  I would assume those could be made part of project template.  Is this correct?

One answer



permanent link
Matt Muller (59813674) | answered Mar 05 '18, 2:39 a.m.

Sean,

Yes I think you are correct - however watch out for the Planned for and Field Against Values as between projects they probably can't be used.

Regards

Matt