![]() I am writing a report where I want to choose a specific iteration in RTC as a parameter. I have three project areas in scope in the report, and only two of the three timelines are up in the filter selection. It seems that the third one needed to have the timeline marked as the "project timeline", so I did that and ran the DCC, but the timeline still isn't showing up. My questions are: 1. What jobs in DCC need to be run to insert timeline data into the data warehouse? Not all of the jobs were selected and so it is possible one of those jobs that wasn't run need to be. 2. Is there something else I need to do to make the timeline selectable? I have the same privileges in all three project areas, so it doesn't seem like that is the issue. |