We are planning to move to a new Project Area in RTC.

In order to retain history of the files which were already in existing Project area, Can components and streams of existing Project area be also moved/copied to new Project Area? so that I can use existing components and streams in new Project area also .

Thanks

0 votes


Accepted answer

Permanent link

 Unlike work items SCM data is not "In a Project Area". The Streams, components and the like are owned by a project area. The owner can be changed and archiving project areas does not affect objects not owned by this PA.

Amit Kumar selected this answer as the correct answer

1 vote

Comments

Thanks Ralph, I got your point,


2 other answers

Permanent link

Take a look at this forum answer: https://jazz.net/forum/questions/227294/is-there-any-way-in-rtc-to-move-a-component-from-one-project-area-to-other-if-yes-does-it-changes-the-uuid-of-the-component


Also, if you want to provide access to users from another project area, take a look at this: https://jazz.net/forum/questions/150465/how-to-setup-streams-with-different-access-control-to-components-for-external-access

0 votes


Permanent link

 Thanks Padur for your quick response.

completely agree with your's aforesaid comments.
Apparently, we are doing same, i.e. accessing components of one project area from other project area by defining access to do so.
But in case we go for decommissioning/archiving of existing project area ( as we are already using new Project area for project management) , it will also loose our components and streams of existing project area which will also impact new project area as new project area will be devoid of streams and components, Isn't ? So, i wanted to move them in new project area.
Is there any solution of this also ? 

Here is my actual requirement,
I wanted to have history of commits in new project area (as per history of existing project area, ) and also don't want to lose them once existing project area get decommissioned OR achieved. 

Thanks

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,202
× 67

Question asked: Jul 06 '17, 12:17 a.m.

Question was seen: 4,459 times

Last updated: Jul 06 '17, 1:00 p.m.

Confirmation Cancel Confirm