 Hi, I have a plan view in the RTC that shows me all WI of my current iteration, but to change te status os this WI I have to enter inside of each one, If I try to select one and move it to another column the plan shows the message: Read-only.

There is a way to change de cards status, I mean from new to inprogress to done for example directly in the plan?
Thanks a lot.

0 votes


Accepted answer

Permanent link

There are different plan types and plan display modes. In iteration plans the Kanban and the Taskboard plan view allow to change the work item states via drag and drop. Quick Planner also supports this. Other plan modes don't as they have a different focus e.g. changing the owner and seeing owner load.

Murilo Valero selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,023

Question asked: Apr 17 '17, 2:44 p.m.

Question was seen: 1,293 times

Last updated: Apr 19 '17, 3:01 a.m.

Confirmation Cancel Confirm