User Story's children task are not showing up in Work Breakdown view

Hi,
In the Work Breakdown view, I noticed that all the children task for all user stories are not being displayed.   Both the User Story and its children Task have the same Planned For schedule.   Any ideas how to resolve this issue?  Thanks in advance.

Enrique

0 votes

Comments
In the plan view, do you have any filter such as "Exclude > Execution Items"?



One answer

Permanent link

Hi Enrique,


Check for two things:
1. Exclude -> Resolved Items is unchecked or not. (If your tasks are in Completed state, and this option is checked, they will not show in plans)
2. Exclude -> Execution Items are unchecked or not, as Lily suggested. (Work items are categorized as Plan Item and Execution Item. Tasks come under execution item. If this option is checked, they will not show in plans).

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,148

Question asked: Feb 08 '17, 11:07 a.m.

Question was seen: 5,154 times

Last updated: Feb 09 '17, 5:12 a.m.

Confirmation Cancel Confirm