How to Create a Project Baseline for Rational DOORs Next Gen version 5.02?

Hi,

I am currently trying to create a Project Baseline in Rational DOORS Next Generation version 5.0.2

How would I create a Project Baseline in DOORS version 5.0.2 ? What are the roles and permissions I would need ?

Please advise, thank you very much.

0 votes



One answer

Permanent link

You need permission for the Project Baseline Administrator operation.
By default, the Project Baseline Administrator role has permission for that operation, but the Administrator and Author roles do not.
In the Project Area properties you can add this role to a member.

When you have your project open in the 'browse artifacts' view, then in the sidebar at the right side of the window, there is a baseline section. There you can create a baseline by clicking the Create a Baseline icon.


See also http://www.ibm.com/support/knowledgecenter/SSYMRC_5.0.2/com.ibm.rational.rrm.help.doc/topics/c_snapshots.html

0 votes

Comments

Thank you for the reply Diana!

Is there a way to do a comparison in [Doors 5.0.2] where I am able to see the new changes made in the current project compared to the baseline ?

Thank you very much

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,029

Question asked: Jan 23 '17, 12:13 p.m.

Question was seen: 8,716 times

Last updated: Jan 23 '17, 3:45 p.m.

Confirmation Cancel Confirm