Customize "Create a new Quality Task" Window shows while creating quality Task in RQM
Hi All,
I have RTC PA and RQM PA associated along with GC enabled. In RQM PA when I try to create quality Task it opens window "Create a new Quality Task" which has first pull down list as work Item types of RTC PA. I want only few work Item types should be shown in pull down list? Is is customizable? If Yes then it needs to customized in RTC or RQM?
I know if we dont provide inline editor to the work item type in RTC, then the respective work Item cant be created using quality Task in RQM. Correct me if I am wrong....
Thank you
One answer
Hi, Kavita
No, this is not customizable in OSLC dialog template currently.
There is a RFE work item which is planned for v6.0.4:
https://jazz.net/jazz02/web/projects/Rational%20Quality%20Manager#action=com.ibm.team.workitem.viewWorkItem&id=68198
You may want to comment there and confirm if that RFE(once implemented) will allow the user to set your own template with less work item type.
Hopefully this helps.
No, this is not customizable in OSLC dialog template currently.
There is a RFE work item which is planned for v6.0.4:
https://jazz.net/jazz02/web/projects/Rational%20Quality%20Manager#action=com.ibm.team.workitem.viewWorkItem&id=68198
You may want to comment there and confirm if that RFE(once implemented) will allow the user to set your own template with less work item type.
Hopefully this helps.