Q re Story Status: Invalid
The "Invalid" story status is defined in the Process Template as:
Why would I want the points associated with these Stories to be included in the
- Invalid: Set by the Product Owner if the story should never be implemented.
'Team Velocity' or
'Story Point Progress' widgets?
I guess that the assumption is that people did the work associated with the Invalid story... hence you should get the points.
Thoughts?
I am using RTC 6.0.1 with the SAFe 3.0 Process (Program) template.
Accepted answer
I don't know what other think or thought........ Since the data collection job and the planning does not exclude this data based on the state, an option to fix this is to set the story points to 0 during the save transition to invalisdusing a custom participant.
See https://jazz.net/forum/questions/222634/set-value-when-saving-a-work-item-type-user-story
for a probably related question. You can also create a defect or enhancement request.
See https://jazz.net/forum/questions/222634/set-value-when-saving-a-work-item-type-user-story
for a probably related question. You can also create a defect or enhancement request.