Q re Story Status: Invalid
![]()
The "Invalid" story status is defined in the Process Template as:
'Team Velocity' or
'Story Point Progress' widgets?
I guess that the assumption is that people did the work associated with the Invalid story... hence you should get the points.
Thoughts?
I am using RTC 6.0.1 with the SAFe 3.0 Process (Program) template.
|
Accepted answer
![]()
Ralph Schoon (62.3k●3●36●43)
| answered Jun 03 '16, 3:12 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
I don't know what other think or thought........ Since the data collection job and the planning does not exclude this data based on the state, an option to fix this is to set the story points to 0 during the save transition to invalisdusing a custom participant.
See https://jazz.net/forum/questions/222634/set-value-when-saving-a-work-item-type-user-story for a probably related question. You can also create a defect or enhancement request. Dan Kaminski selected this answer as the correct answer
Comments Hi Ralph -
Thanks for your response.
It seems illogical that points associated with a Story would count toward velocity... I will submit a Defect and see what happens.
Thanks Again !
Dan
|