The "Invalid" story status is defined in the Process Template as:
  • Invalid: Set by the Product Owner if the story should never be implemented.

Why would I want the points associated with these Stories to be included in the 
'Team Velocity'              or
'Story Point Progress'        widgets?

I guess that the assumption is that people did the work associated with the Invalid story... hence you should get the points.

Thoughts?

I am using RTC 6.0.1  with the SAFe 3.0 Process (Program) template.

Accepted answer


permanent link
Ralph Schoon (63.1k33646) | answered Jun 03 '16, 3:12 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
I don't know what other think or thought........ Since the data collection job and the planning does not exclude this data based on the state, an option to fix this is to set the story points to 0 during the save transition to invalisdusing a custom participant.

See  https://jazz.net/forum/questions/222634/set-value-when-saving-a-work-item-type-user-story
for a probably related question. You can also create a defect or enhancement request.

Dan Kaminski selected this answer as the correct answer

Comments
Dan Kaminski commented Jun 07 '16, 3:42 p.m.

  Hi Ralph - 


Thanks for your response.  

It seems illogical that points associated with a Story would count toward velocity...  I will submit a Defect and see what happens.

Thanks Again !
Dan