Could you explain to me how RTC 4.0 calculates the load time

  Hello,

I have an iteration  which has 1 day long.

I have 1 dev team member who is at 20% for that iteration and has workday length of 8 hours

If I do simple calculation of 20% of 8 hours that gives me 1.6 h available but RTC gives me 1.75h available 

  So could some one explain to me how RTC calcules the time available to do work in an iteration?

Thank you.

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,221

Question asked: May 16 '16, 2:40 p.m.

Question was seen: 1,766 times

Last updated: May 17 '16, 12:04 p.m.

Confirmation Cancel Confirm