How can I creat a Plan for different Timelines?
Hello, I saw this question on FAQ, but the date was 2013, I would like to know if there some change.
I have in my project 5 different timelines. There is a way to create a kambam view with information about the backlog of all timelines? I just can select one when I try to create a plan. Or if I create one plan for each timeline can I show all in one view or dashboard ? Thank you. |
Accepted answer
Ralph Schoon (63.1k●3●36●46)
| answered Apr 01 '16, 1:01 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER edited Apr 01 '16, 1:02 a.m.
Any plan can always only select one iteration in its configuration, this means a plan can only look at one timeline at a time. You could use cross project planning to track progress across multiple timelines, but it is a lot more manual. See https://jazz.net/wiki/bin/view/Deployment/RTCProcessFundamentals for some considerations.
Murilo Valero selected this answer as the correct answer
|