Quickplanner -clarification

CLM 5.0.2ifix 003

Hello,

Quickplanner question:

In the backlog, I have 20 stories, with 4 tasks each. When viewing the backlog in QuickPlanner, it states that I have 20 items, not (20x4) 80 items...is this correct? It will only count plan items or parent items?

0 votes



One answer

Permanent link
I see execution items and plan items in my backlog in RTC (6.0.1) quick planner. The count is also accurate as far as I can tell.
Please note, just because a work item is a child of a work item that is planned for the backlog, does not make that child automatically planned for the backlog. I assume you did not plan the child items for the backlog and the count is accurate therefore.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019
× 7,495
× 239

Question asked: Mar 24 '16, 12:15 p.m.

Question was seen: 4,088 times

Last updated: Mar 29 '16, 5:17 a.m.

Confirmation Cancel Confirm