Hello,
Quickplanner question:
In the backlog, I have 20 stories, with 4 tasks each. When viewing the backlog in QuickPlanner, it states that I have 20 items, not (20x4) 80 items...is this correct? It will only count plan items or parent items?
|
One answer
Ralph Schoon (63.3k●3●36●46)
| answered Mar 29 '16, 5:16 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER edited Mar 29 '16, 5:17 a.m.
I see execution items and plan items in my backlog in RTC (6.0.1) quick planner. The count is also accurate as far as I can tell.
Please note, just because a work item is a child of a work item that is planned for the backlog, does not make that child automatically planned for the backlog. I assume you did not plan the child items for the backlog and the count is accurate therefore. |
Your answer