Approximate upgrade times

Good day,

We are performing an upgrade from CLM v5.0.2 to v6.0.

We would just like to get an indication of the time it will take to run each script depending on the size of the DB's? The previous upgrade was fairly quick, however there is no online migration for RQM - which normally takes the longest.

Thank-you,
Regards,
Michael Alberda

0 votes



One answer

Permanent link
Hard to tell Michael,

I would suggest to set up a test system with your current back up and run a test upgrade on that to get a detailed step list and a good sense of how much time you need.

Please be aware that you can upgrade the applications one by one. You can pick an order that works best for you and don't usually have to perform all upgrades on one weekend/night.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 7,503
× 267

Question asked: Feb 26 '16, 6:25 a.m.

Question was seen: 2,134 times

Last updated: Feb 26 '16, 6:42 a.m.

Confirmation Cancel Confirm