Why is this Gantt chart messed up?
I am using the formal project management template, but not the RUP phases. I defined an iteration type called milestone (which is actually a phase, but manager wanted it that way). The working hours are set to 8, I have set Finish No Later than and associated dates. Yet the Gantt shows a 2 day task extending over about 6 weeks, and so on throughout the plan.
It seems I ned a rep score before I can actually attach a snapshot (doh!!). So not sure how I am going to illustrate the problem.
Accepted answer
Steve,
Have you look at your Work Allocations Associate resources to teams and timelines:
If you / or the person is working 100% on that project then yes; if not it will extend?
Just something to consider it may not be your problem.
Regards
Matt Muller
Comments
Hi Matt,
Thank you so much. It took me a wee while to figure out what resources tab you meant, but running a quick test does seem to fix my problem.
Best regards
Steve
Hi Steve,
No problem glad I could help; I'm an RTC consultant and always looking for new clients to help: My email is seslimited@Hotmail.co.uk
Regards
Matt