RQM: Reconcilation - Linked test case occur multiple times - bug or feature?
Hello,
during reconcilation RQM shows linked test cases multiple times per requirement:
In the attached screen shot for each requirement a linked test cases is shown 4 times.
I assume the reason is, that we have already 4 snapshots for the test plan and also 4 snapshots for each single test case.
Is there any reason (feature?) or is this a bug?
We are using RQM 5.0.2 together with DOORS 9.6.
thanks you, Jörg
during reconcilation RQM shows linked test cases multiple times per requirement:
In the attached screen shot for each requirement a linked test cases is shown 4 times.
I assume the reason is, that we have already 4 snapshots for the test plan and also 4 snapshots for each single test case.
Is there any reason (feature?) or is this a bug?
We are using RQM 5.0.2 together with DOORS 9.6.
thanks you, Jörg
Accepted answer
Hi Jörg,
this is an already reported bug.
We already discussed with IBM and it is an accepted defect.
For further information please contact me.
Regards
Jochen
this is an already reported bug.
We already discussed with IBM and it is an accepted defect.
For further information please contact me.
Regards
Jochen
One other answer
I've created a Defect 148362 since I'm not able to update the PMR and the hint regarding snapshot might be helpful.