Constraint Date vs Due Date
All,
In the Formal Process Template, what will the Constraint Date and Due Date give me? By that, something is due on 3/8. If I choose Due Date = 3/8, does RTC due something? If I choose Finish No Later than 3/8 for the Constraint fields, does RTC due something different? thanks |
Accepted answer
I am not certain, but I think due date is simply a timestamp attribute that is used to store a due date for a work item, while constraint date (and type) are used in planning/scheduling. See links below for related information:
https://jazz.net/forum/questions/109071/due-date-vs-finish-no-later-than-whats-the-differences The following link shows an example on extending the use of due date: https://rsjazz.wordpress.com/2015/10/16/due-date-notifier-an-asynchronous-task-example/ Mahari Hill selected this answer as the correct answer
|