As part of our Jazz evaluation, we've recently started planning the next release of the J9 VM and we're run into a few difficulties.

Our product is divided into multiple components, each with its own team area and category to match. We then have iterations matching a release (ie Java6 SRx) which contains multiple milestones. As part of the warm-up to the next release we plan the features and fixes that will go into it (Java6 SRx).

What we would like to do is have a SRx plan for all teams (and all milestones) so we can see everything for that release in one place. We can't do that with the way iteration plans work right now. Before M4 we could at least create a plan for SRx and choose all categories. Work Items would be planned for SRx initially and after the plan was "complete" we'd move each task to its "planned for" milestone. Now that we've moved to M4 that's not possible.

The way we see it, the plan for for overall iteration should show all work items for categories that are children of the team area's category. Also, we would like this overall plan to show work items scheduled for milestones below it. This way even after we move an item to Milestone 1 we can still see it in SRx (since SRx is a parent iteration of Milestone 1).

Is there a way to do what we want?

0 votes



2 answers

Permanent link
gcastro schrieb:
As part of our Jazz evaluation, we've recently started planning the
next release of the J9 VM and we're run into a few difficulties.

Our product is divided into multiple components, each with its own
team area and category to match. We then have iterations matching a
release (ie Java6 SRx) which contains multiple milestones. As part
of the warm-up to the next release we plan the features and fixes
that will go into it (Java6 SRx).

What we would like to do is have a SRx plan for all teams (and all
milestones) so we can see everything for that release in one place.
We can't do that with the way iteration plans work right now. Before
M4 we could at least create a plan for SRx and choose all categories.
Work Items would be planned for SRx initially and after the plan was
"complete" we'd move each task to its "planned
for" milestone. Now that we've moved to M4 that's not
possible.

The way we see it, the plan for for overall iteration should show all
work items for categories that are children of the team area's
category. Also, we would like this overall plan to show work items
scheduled for milestones below it. This way even after we move an
item to Milestone 1 we can still see it in SRx (since SRx is a parent
iteration of Milestone 1).

Is there a way to do what we want?


I suggest you file an enhancement request against the Agile Planning
component.

Cheers,
Tobias

0 votes


Permanent link
For those interested, this is being tracked by Enhancement 38695: https://jazz.net/jazz/web/projects/Jazz%20Project#action=com.ibm.team.workitem.viewWorkItem&id=38695

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Dec 03 '07, 9:05 a.m.

Question was seen: 4,933 times

Last updated: Dec 03 '07, 9:05 a.m.

Confirmation Cancel Confirm