Leesen Padayachee (9943115) | asked Nov 16 '15, 4:05 a.m.

Hi

Is it possible to have multiple tasks per Test Plan section? At the moment, I have to remove a task associated to a test plan section before adding another one. My client requires multiple tasks per section of the test plan.

Thanks

Leesen

One answer



permanent link
paul chu (59411) | answered Nov 16 '15, 10:49 a.m.
JAZZ DEVELOPER
Each editor section can associated to only one quality task.  The quality task can have sub-tasks, but they would be managed within the change management application. 