RQM 5.0 Requirements Traceability Report Project is blank
Accepted answer
Hi Paul,
Make sure there are Requirement Collections linked to the appropriate RQM Test Plans. Also, make sure the Data Collection jobs (ETL's) are successfully running. The Requirements Traceability report gets the data from the Data Warehouse, therefore depends on the successful completion of the ETL's.
Thank you,
Clara Forero
Make sure there are Requirement Collections linked to the appropriate RQM Test Plans. Also, make sure the Data Collection jobs (ETL's) are successfully running. The Requirements Traceability report gets the data from the Data Warehouse, therefore depends on the successful completion of the ETL's.