Import of project plan from excel to RTC
![]()
Bhawna Gupta (21●10)
| asked Sep 09 '15, 1:51 a.m.
retagged Sep 18 '15, 4:03 p.m. by Ken Tessier (841●1●7) Hi,
I have an yearly work plan that is seggregated quaterly in an excel sheet. Is there a way i can import it to RTC plan.
Any suggestions/guidance in this regard will be helpful.
Thanks Bhawna |
2 answers
![]()
Hi Bhawna,
You can Import\Export and open a plan as an XML file. The Excel sheet Import, I see the below RFE created. https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=170339 Regards, Arun. |
![]()
For details about importing from an XML file, see Importing and exporting plans with Microsoft Project.
Ken
|