 Hi

Is it possible to merge work items (consolidate) from two separate project area's and retain the history and attachments from the all the work items. In other words the work items that we will be moving, can they be moved in bulk and keep their history and any attachments so that it is present in the new project area?

Thanking you in advance

Glenn

1 vote


Accepted answer

Permanent link
If the project areas are on the same server, then yes they can be moved.  I know that you can open each one and change the project area.  If the work item definitions are different between the two project areas, then you may end up "losing" some of the attributes.

You can also programmatically do this (write a java program using the java APIs), while in the process mapping attributes from the "old" work item definition to the "new" work item definition as needed.

However, unless something has changed in V6 .. you can't do this and retain history if they span servers. 
Glenn Watkins selected this answer as the correct answer

2 votes

Comments

 Hi Susan


Thank you very much for taking the time to respond, you have really helped.

Glenn

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,033

Question asked: Sep 08 '15, 9:06 a.m.

Question was seen: 1,758 times

Last updated: Sep 11 '15, 4:13 a.m.

Confirmation Cancel Confirm