TestSuite for planning TC execution
Hi,
As a old user og ALM (QualityCenter), I´m used to make the planning of what TC must be execetuted in what week. E.g is TestSuite - "Week 41", all the test cases that I have planed for this week and so on.
I know we have "Test Schedules" in a TestPlan, but I do only see this to conflict using a TestSute for week 41 or dos it?
BR
Thor
|
Accepted answer
I would suggest you create iterations for the weeks (e.g. Week 1, Week 2, etc.) in your schedule (see Timelines and Iterations in Rational Quality Manager) and create/assign test suite execution records against those iterations.
Thor Aaen selected this answer as the correct answer
|