On Taskboard why do Tasks show "Story" column and not appropriate "Status" column?
One answer
Scott,
in that first column appear all Plan Work items. This can be defined in the Process Configuration.
Check in the Process configuration of the Project Area - Project Configuration - Configuration Data - Planning - Work Item Type Categorization. All the selected Work item types here will appear in the first column and stay there regardless the state.
/Elisabeth
in that first column appear all Plan Work items. This can be defined in the Process Configuration.
Check in the Process configuration of the Project Area - Project Configuration - Configuration Data - Planning - Work Item Type Categorization. All the selected Work item types here will appear in the first column and stay there regardless the state.
/Elisabeth