On Taskboard why do Tasks show "Story" column and not appropriate "Status" column?
All my user stories and tasks are in the 1st column "Story" on the Taskboard. The tasks have different status but they do not appear in that status column. All the columns are grayed out if I try to move the task to the status column (i.e. "In-Progress", "New", etc.).
|
One answer
Scott,
in that first column appear all Plan Work items. This can be defined in the Process Configuration. Check in the Process configuration of the Project Area - Project Configuration - Configuration Data - Planning - Work Item Type Categorization. All the selected Work item types here will appear in the first column and stay there regardless the state. /Elisabeth Comments
scott lindberg
commented Aug 06 '15, 11:14 a.m.
Hi Elisabeth,
Hello Scott,
scott lindberg
commented Aug 07 '15, 12:32 p.m.
Hi Elisabeth,
|
Your answer