On Taskboard why do Tasks show "Story" column and not appropriate "Status" column?

All my user stories and tasks are in the 1st column "Story" on the Taskboard. The tasks have different status but they do not appear in that status column. All the columns are grayed out if I try to move the task to the status column (i.e. "In-Progress", "New", etc.).

1 vote



One answer

Permanent link
Scott,
in that first column appear all Plan Work items. This can be defined in the Process Configuration.
Check in the Process configuration of the Project Area - Project Configuration - Configuration Data - Planning - Work Item Type Categorization. All the selected Work item types here will appear in the first column and stay there regardless the state.

/Elisabeth

2 votes

Comments

Hi Elisabeth,
What do I need to change at "Process configuration of the Project Area - Project Configuration - Configuration Data - Planning - Work Item Type Categorization" in order for them to appear in the correct 'Status' columns.
Thanks, Scott

Hello Scott,
all work item types that are selected (checked ) there are plan items and appears in the first column. If Task is selected, uncheck it. Save the Project Area.

Does this help?
/Elisabeth

Hi Elisabeth,

That did it.

Thanks very much - enjoy the weekend,
Scott

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220

Question asked: Aug 06 '15, 10:31 a.m.

Question was seen: 4,004 times

Last updated: Aug 07 '15, 12:32 p.m.

Confirmation Cancel Confirm