Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Date Issue!

Hi,

We've noticed that when setting the dates for the milstone and release plan, one can set a date for the release plan which is prior to the end of a milestone plan. This also occurs when creating parents and children workitems links. that is: parent due date is before the childs due date. is there a way to control such thing from the process specification?

thanks

0 votes



4 answers

Permanent link
In the process under the com.ibm.team.workitem.operation.workItemSave operation, you might be able to accomplish what you want with the com.ibm.team.workitem.advisor.impliedProperties advisor.

0 votes


Permanent link
Our current implementation only marginally pays attention to the
semantics of dates. This is true inside single components (see your work
item example or inconsistencies you can produce between iterations of
the same project area) and between components (see your planning example).

In order to improve the situation we need to assess which of constraints
are 'natural' and therefore would have to be implemented by the
components. I'd put the dates of the iterations of a project area into
this category. Other constraints don't hurt the system but users might
want to enforce them. Those should be definable in the process
specification as you propose. We have most of the hooks in place (i.e.
most of the relevant operations can be impacted by the process
specification) but we are missing the right advisors/precondition
checkers at this point in time.

Cheers, Kai



farrugiarobert wrote:
Hi,

We've noticed that when setting the dates for the milstone and release
plan, one can set a date for the release plan which is prior to the
end of a milestone plan. This also occurs when creating parents and
children workitems links. that is: parent due date is before the
childs due date. is there a way to control such thing from the
process specification?

thanks

0 votes


Permanent link
Hi,

So will the date issue be arranged or do we need to specify the criteria within the process specification.... If so, is there a way to view how this can be done.

Thanks in advance

0 votes


Permanent link
- consistency between dates of iterations is on the 0.6 plan
- aligning the semantics of dates across components in general is not on
the 0.6 plan, however individual components may look into some of the
issue for 0.6 but have to tell themselves what they will do
- you can not specify your constraints in the process specifications as
we are missing the necessary advisors/precondition checkers, providing
those is not on the 0.6 plan

Cheers, Kai


farrugiarobert wrote:
Hi,

So will the date issue be arranged or do we need to specify the
criteria within the process specification.... If so, is there a way
to view how this can be done.

Thanks in advance

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Nov 12 '07, 5:59 a.m.

Question was seen: 6,150 times

Last updated: Nov 12 '07, 5:59 a.m.

Confirmation Cancel Confirm