I would like to customize my process with pre-defined team areas. So I went to the "Work Items Categories" tab and defined all the "team areas" there.
But when I create a new process template based on that Proj.Area where I did the customization, those team areas are lost (no kept on the new proc.template).
Is this a bug? Or works as designed?
Want to double check with the community to see if I am doing anything wrong or I should open a defect/change request to the Rational team.
Thanks
Claudia

0 votes



3 answers

Permanent link
Team areas and work item categories are not included when a template is created from a project.

You can create an enhancement request here:

https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=jazz.viewPage&id=com.ibm.team.workitem

---
Ryan Manwiller
Jazz Team

0 votes


Permanent link
I've found a way to partially do this: instead of creating the categories and team areas in the "Work Items Categories" tab, I've defined them within the "Process Configuration" tab (Project Area Initialization --> Setup project & Create Team Areas options).
In this way when I create a process template this information is kept, so the next project area based on this proc.template will be initialized with this info.

The only I'm missing in this initialization is the ASSOCIATION between the categories and the team areas. Is there any way to keep this info?
I believe the inizialization process is not considering this association...

Can anybody clarify this? Thanks in advance,
Claudia Callegari

0 votes


Permanent link
I also couldn't find a way to initialize in a project template the
association between the categories and the team areas.

I've submitted work item 86119 for this.

Cheers,
Geoff

ccalleg wrote:
I've found a way to partially do this: instead of creating the
categories and team areas in the "Work Items Categories"
tab, I've defined them within the "Process Configuration"
tab (Project Area Initialization --> Setup project & Create
Team Areas options).
In this way when I create a process template this information is kept,
so the next project area based on this proc.template will be
initialized with this info.

The only I'm missing in this initialization is the ASSOCIATION between
the categories and the team areas. Is there any way to keep this info?

I believe the inizialization process is not considering this
association...

Can anybody clarify this? Thanks in advance,
Claudia Callegari

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jun 10 '09, 11:09 a.m.

Question was seen: 6,246 times

Last updated: Jun 10 '09, 11:09 a.m.

Confirmation Cancel Confirm