Display Current start date and end date in RTC Work Item Editor

Following can be displayed:
Planned start date & end date (based on the "Planned" snapshot) in the work item editor & plan view.
Actual start date (timestamp of Work Item InProgress) in the plan view.
Proposed start date and end date (timestamp based on "Proposed" snapshot)

How to display the current start date and end date of the work item (i.e., dates that appear in the Gantt chart) in the plan view or the Work Item ?

0 votes



One answer

Permanent link
There are OOB attributes for Due date, but none for start date. You can either create an attribute using timestamp type, where the user would need to set it himself. If you want to dynamically inherit this information from somewhere else, you can try to create a script based value set, but I am unaware of the logistics in doing so.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,132

Question asked: Jul 14 '14, 9:29 a.m.

Question was seen: 4,402 times

Last updated: Jul 15 '14, 11:04 a.m.

Confirmation Cancel Confirm