How can I prevent further test execution in an approved or retired plan?


Michele Pegoraro (1.8k14119103) | asked May 08 '15, 5:33 a.m.
Hi,
I'd like to block further test executions on a plan that has been approved (or retired). Is it possible?

Thanks,
Michele.

Accepted answer


permanent link
Paul Slauenwhite (8.4k12) | answered May 14 '15, 8:43 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
Unfortunately, this is not supported (you may want to open a RQM enhancement).  However, you could assign all the TCERs to the test plan owner and enable the 'Disallow Execution of Test Case Execution Record if owner is not executing it' precondition.