Hi everyone, I am trying to link project from RQM to requirement in DOORs. Can someone direct me how to perform this configuration.
Here is what i tried to do below but couldn't succeed
1. Under Planning I click The test Plan i already created.
2. I click Requirement
3. Then I click Create
4. I got this message below:
Provider Configuration:"No provider configured for task tracking, please consult your administrator for more details!"
|
One answer
Hi Collins,
I am not sure which releases of the tools you are using, but here is the 5.0.2 link for setting up Rational DOORS 9 with RQM: http://www-01.ibm.com/support/knowledgecenter/SSJJ9R_5.0.2/com.ibm.rational.test.qm.doc/topics/t_config_doors.html Please let me know if after doing this you are still experiencing the same issue. Kind regards, Paul Comments
Collins Akin
commented Apr 01 '15, 10:58 a.m.
I am using RQM 5.0 and Rational Door Next Generation is 5.0 Ah - that should be simpler then. Assuming you've registered both applications with the same JTS, follow this forum post:
|