I am looking at Iteration Planning, to move items from the Backlog right to Sprints, can I do this without viewing the Releases "tab/card"? How can I remove Release?

thanks

0 votes


Accepted answer

Permanent link
You can click on the "pin" operation (upper right hand corner) of the Backlog view, and then scroll over to the iteration you want.   So you cannot "remove" the Release pane, but you can scroll past it to the one you want.
Mahari Hill selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,023
× 7,498
× 239

Question asked: Mar 30 '15, 1:30 p.m.

Question was seen: 3,469 times

Last updated: Mar 31 '15, 1:05 p.m.

Confirmation Cancel Confirm