RTC 5.0.2 Timelines widget issue
Hi all
in RTC 5.0.2, we're encountering an issue with the Timelines widget. Basically in all of our project areas, the widget defaults to the top-most timeline & even when we edit the parameters to be a Team (that has a different timeline), the widget does not change to show the Team's timeline iterations. It stays stuck at the topmost iteration. Each project area does not have a project timeline defined if that helps pinpoint the issue. Thanks for any help! |
2 answers
Hello,
Does anybody receive any feedback for this issue? Are those widgets part of RTC standard delivery? And can we submit a defect for this widget behaviour? @Jazz + RTC devs: please help. Thanks, Tuan |
Hi @manoj.panda,
I have just tested this issue in case of RTC 6.0 and am not able to reproduce it. Could you please confirm that it was fixed in the RTC 6.0? Thanks, Tad |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
Hi Mark,
It is difficult for me to understand this issue. Can you provide screen snapshot of the issue?
Hi Krzysztof sorry here are some screenshots
Timeline structure in area
Team Area we want to use
The widget always uses the top most timeline even when we adjust the settings
Hi,
I checked using 5.0.2. Looks like if the project using scrum template, then i am not getting the expected timelines in dashboard. But its works in another project using formal project management template. here is the screenshot.
Hi,