Hi All, 
I look at my Integration stream and it has:

Component1 (59:2015.107.1708)
Component2 (70:2015.107.1512)
Component3 (72:2015.107.1512)

and my build workspace has

Component1 (57:2014-09-19)
Component2 (66:2014.1201.1050)
Component3 (70:2014-09-19)

How can I fix this? Is this a workspace or stream problem?

0 votes


Accepted answer

Permanent link
Hi Daniel,
The difference is the baseline of the component. You can accept the latest baselines from "Pending Changes" view manually.

If you use the RTC build definition, when you create the build definition, you need to make the following selection:
- enable "Jazz Source Control" pre-build
- in the "Jazz Source Control" tab, tick "Accept latest changes before loading"
- ensure the build workspace's flow target stream is the integration stream
After that when you start a build, the build workspace will accept all latest changes from the integration stream first, then start build.
Daniel Ruebush selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jan 12 '15, 2:56 p.m.

Question was seen: 2,695 times

Last updated: Jan 12 '15, 7:09 p.m.

Confirmation Cancel Confirm