Can I limit estimation of Tasks to only hours (not days or weeks)?


Daniel Gilio (102124) | asked Dec 09 '14, 4:41 p.m.
edited Dec 09 '14, 4:42 p.m.

In RTC, we do not want our users estimating stories in terms of days or weeks but only in hours. Is there a way to enforce this behavior on the Estimate field? Right now it allows for Second, Minute, Hour, Day and Week. We want to enforce that stories are estimated based only on hours.

Please advise

One answer



permanent link
Ralph Schoon (63.1k33645) | answered Dec 10 '14, 3:28 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Have you tried this?


Your answer