Is it possible to sequence work items?

 Using RTC 4.0.6:
We are planning to derive a work item type called "Change Request", that could be used for various types of document change, 1 work item per type of document e.g.Requirements specs, Design Specs, Test Cases. Is there a possibility to to sequence the work items such that Test cases cannot be initiated until Requirements Specs have changed?

0 votes



2 answers

Permanent link
Have a look at depends on link type.
You can't solve the TestCases until the ReqSpec is solved.

1 vote


Permanent link
I have tested those links and it does not stop or error out from closing the Test case related Work item prior to Requirement work item!
All this does is shows a link and if closed, then the closed item appears struck out, thats all.
Can you confirm or advise if there is any associated operational behaviour that could be added to these link types?
or any other alternative?

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Oct 23 '14, 4:29 p.m.

Question was seen: 2,415 times

Last updated: Oct 24 '14, 10:59 a.m.

Confirmation Cancel Confirm