If I am using WI to promote in RTC can I assign it after the stream build


Rene McAllister (122) | asked Oct 15 '14, 12:16 p.m.
We are using RTC and would like to only associate a WI to a changeset once it is ready to be pormoted to another stream.  If the WI is assinged after the stream build, will another build be mandatory?

One answer



permanent link
Tim Mok (6.6k38) | answered Oct 16 '14, 10:22 a.m.
JAZZ DEVELOPER
 Associating a work item to a change set doesn't alter the change set. It will not trigger another build. Your first build will still contain that change set.