How can I add new existing report resource for the project setup ?
I want to add the existing report resource "Micro Open vs Closed Work Items" in the project setup for Reports to ensure the availability in new project areas.
How can I do this ? |
Accepted answer
Katrin, you need to edit the Project Area Initialization of the process template. There you can specify what report resources you want automatically deployed on project area creation.
Katrin Heymann selected this answer as the correct answer
|