Hi
I have a requirement to roll up efforts of children to parent (balance effort). For e.g. I have a Parent work Item called TESTING-TASK with an estimate of 32 hrs Two Child TASKSNow when I close child TASK 1 the Parent task should show a balance of 24 hrs. Is there a way to do it or a script to achieve the above. Regards Niranjan V |
One answer
Ralph Schoon (63.6k●3●36●46)
| answered Jul 28 '14, 3:25 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
If the tasks are planned for the same iteration, I think the planning component should give you that.
If you have a more special need, https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/ describes ways to roll up across a parent child relationship. Comments
V Niranjan
commented Jul 28 '14, 9:27 p.m.
Hi Ralph
|
Your answer