Hi

I have a requirement to  roll up efforts of children to parent (balance effort).

For e.g. I have a Parent work Item called TESTING-TASK with an estimate of 32 hrs
Two Child TASKS

TASK 1 - Estimate of 8 hrs
TASK 2 - Estimate of 24 hrs
Now when I close child TASK 1 the Parent task should show a balance of 24 hrs. Is there a way to do it or a script to achieve the above.

Regards
Niranjan V





0 votes



One answer

Permanent link
If the tasks are planned for the same iteration, I think the planning component should give you that.

If you have a more special need, https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/ describes ways to roll up across a parent child relationship.

0 votes

Comments

Hi Ralph

The planning component does not give me the view which I need. I need the parent task to have the balance effort  if the child tasks are completed.

Regards
Niranjan V

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,029

Question asked: Jul 27 '14, 9:56 p.m.

Question was seen: 4,572 times

Last updated: Jul 28 '14, 9:27 p.m.

Related questions
Confirmation Cancel Confirm