Susan Hanson (1.6k2201194) | asked Jul 22 '14, 9:04 a.m.
Is there a way to configure this for a project area?

Comments
Robert Wen commented Jul 22 '14, 9:14 a.m.

Can you provide some more details?  I see a couple of places in the Process Configuration tab for a Project Area where an admin (or someone with appropriate privileges) can make some alterations regarding approvals. 


Susan Hanson commented Jul 22 '14, 9:18 a.m.

From your change sets, you can right-click and do "Submit for Review".  This prompts with a dialog where you can Select approvers for the change sets along with a Subject and Due Date and RTC will generate an approval of type Review.  The default text seems to be "Review" for the Subject.  We'd like to change that to default to "Code review".

One answer



permanent link
Tim Mok (6.6k38) | answered Jul 22 '14, 9:31 a.m.
JAZZ DEVELOPER
Unfortunately, it is not configurable.