It's all about the answers!

Ask a question

how migrate the data from a server with RQM 3.1 to other server with RQM 4.0.x?


Cristian Zárate (1858) | asked Jun 25 '14, 8:28 a.m.
 Hi, I need migrate the data from a server with Rational Quality Manager 3.1 to other server with Rational Quality Manager 4.0.x. Is there any guide in order to do this migration?

Thanks in advice.

2 answers



permanent link
Ara Masrof (3.2k15) | answered Jun 25 '14, 8:47 a.m.
JAZZ DEVELOPER
Cristian,
There is no built in way to migrate data from version 3.x on one server to version 4.x to another server
Your options would be to :
  • Upgrade the existing 3x sever to 4.x
  • You can then use the RQM copy Utility (https://jazz.net/wiki/bin/view/Main/RQMCopyUtility) to copy assets from one serer to the other
It is important to note, the function of the RQM Copy Utility is 'not' for a full project copy, but rather copying specific assets from the project area (on one server) to another server.
Please review the Copy Utility wiki for a full overview of it capabilities and known limitations 

Ara

permanent link
Cristian Zárate (1858) | answered Jun 25 '14, 9:26 a.m.
 Thanks Ara

Your answer


Register or to post your answer.