It's all about the answers!

Ask a question

Best guess and Optimistic in Advanced Release Burndown report


Bentsi Magidovich (2036) | asked May 20 '14, 1:11 p.m.
 Hi,
Could someone explain please how the best guess and optimistic estimates are calculated in Advanced Release Burndown report.
Thanks.

One answer



permanent link
Peter DeRosa (334) | answered Jun 03 '15, 2:10 p.m.

Not sure if you were using the old bar chart or the new line chart, but I believe the algorithm was the same as follows:

  • Best Guess: Projects using average of last 3 iteration velocities
  • Optimistic: Projects using average of best 3 from last 6 iteration velocities
  • Pessimistic: Projects using average of worst 3 from last 6 iteration velocities

I did go verify, but I think you actually need to include the required history data (i.e. 3 or 6 iterations) in the chart or it won't do the forecasts.  I would prefer that it could go get the data for the purposes of forecasting, but not have to include them in the chart (because often those iterations aren't part of the current "release").

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.