Change progress bars on plans lists to show by points instead of hours?
It's possible to change how progress bars are displayed within a plan from the default hours to story points.
But in the plans lists views such as All Plans or Current Plans if the progress bars are displayed they always show hours. Is there a way to change this to story points for groups not using hours in their work items? |
One answer
There are some progress bar will show story points by default such as Release backlog. All plans are able to use toggle to show different way: from story point to hours or vice verse. You can open the plan and click on the progress bar to toggle the display. I dont think there is a way to change the default display though.
|