Progress Rollup for Nested Iterations

Hi,

We have created an iteration plan with phases - each phase has 1..n iterations. Is there an easy way to view progress at each level (iteration, phase, project)?

Thinking I'm just missing something.

Thanks!

0 votes



3 answers

Permanent link
Hello,

in RTC Beta 2 you can in addition to Iteration Plans create Release Plans. A release plan can be created for any iteration, and includes all work items planned for that iteration plus all work items planned for a child iteration and belonging to the group of top-level work item types.

Please see section "Support for Release Plans" in New & Noteworty on https://jazz.net/downloads/rational-team-concert/betas/2.0Beta1?p=news

Does this answer your question?

/Elisabeth

0 votes


Permanent link
Hi,

release plans are to be used to track the progress of an overall release
in terms of its top level items. The progress is shown in a customizable
sizing attribute (in Scrum story points) not in hours since future
iterations are typically not broken down yet, so no concrete hour
estimates exist yet.

Dirk Bumer
Agile Planning Component

ehodel wrote:
Hello,

in RTC Beta 2 you can in addition to Iteration Plans create Release
Plans. A release plan can be created for any iteration, and includes
all work items planned for that iteration plus all work items planned
for a child iteration and belonging to the group of top-level work
item types.

Please see section "Support for Release Plans" in New &
Noteworty on
https://jazz.net/downloads/rational-team-concert/betas/2.0Beta1?p=news

Does this answer your question?

/Elisabeth

0 votes


Permanent link
Thanks :)

Hi,

release plans are to be used to track the progress of an overall release
in terms of its top level items. The progress is shown in a customizable
sizing attribute (in Scrum story points) not in hours since future
iterations are typically not broken down yet, so no concrete hour
estimates exist yet.

Dirk Bumer
Agile Planning Component

ehodel wrote:
Hello,

in RTC Beta 2 you can in addition to Iteration Plans create Release
Plans. A release plan can be created for any iteration, and includes
all work items planned for that iteration plus all work items planned
for a child iteration and belonging to the group of top-level work
item types.

Please see section "Support for Release Plans" in New &
Noteworty on
https://jazz.net/downloads/rational-team-concert/betas/2.0Beta1?p=news

Does this answer your question?

/Elisabeth

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Apr 01 '09, 1:57 p.m.

Question was seen: 4,406 times

Last updated: Apr 01 '09, 1:57 p.m.

Confirmation Cancel Confirm