In plans, how to set so that only closed WI have strike through?

How do you change which work items have strike-through display in plans? At present, WI such as those with status Resolved or Done are displayed with a strike-though. It looks like the setting is somewhere in the Project Area configuration under Workflows settings.



We found the below forum link, but after trying various settings it didn't seem to make a difference.
https://jazz.net/forum/questions/111705/children-listed-on-links-tab-are-displayed-with-strikethrough-font

BTW we also tried ticking "Show resolution" under States section, but this also did not seem to change the display.

0 votes


Accepted answer

Permanent link
I think the states that are in the Closed group are shown with strikethru.

each workitem workflow sets that.
Ian Wark selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019

Question asked: Mar 17 '14, 4:21 a.m.

Question was seen: 3,138 times

Last updated: Mar 17 '14, 6:29 a.m.

Confirmation Cancel Confirm