Steve,
You need to enable QM to support multiple timelines and team areas first. See the details here:
https://pic.dhe.ibm.com/infocenter/clmhelp/v4r0m6/index.jsp?topic=%2Fcom.ibm.rational.test.qm.doc%2Ftopics%2Ft_enable_team.html
Then as you found out, you can create multiple timelines and use them:
https://pic.dhe.ibm.com/infocenter/clmhelp/v4r0m6/index.jsp?topic=%2Fcom.ibm.rational.test.qm.doc%2Ftopics%2Ft_setup_timeline_iteration_team.html
Hope this helps.
Don
You need to enable QM to support multiple timelines and team areas first. See the details here:
https://pic.dhe.ibm.com/infocenter/clmhelp/v4r0m6/index.jsp?topic=%2Fcom.ibm.rational.test.qm.doc%2Ftopics%2Ft_enable_team.html
Then as you found out, you can create multiple timelines and use them:
https://pic.dhe.ibm.com/infocenter/clmhelp/v4r0m6/index.jsp?topic=%2Fcom.ibm.rational.test.qm.doc%2Ftopics%2Ft_setup_timeline_iteration_team.html
Hope this helps.
Don
Comments
steve Hill
Mar 12 '14, 5:26 p.m.I found the iteration setting under project timelines.