Burndown template in reporting

What exactly the Burndown report template shows thes user?
I have completed my iteration and closed all the work item in the iteration. Once the iteration is complete I think the Burndown need to meet to zero in graph (report).
However I am not getting that as my report. it does not touch zero in graph. any help

0 votes



One answer

Permanent link
The first and last points of the Burndown chart equal the start and end times of the iteration. So if you close the work items after the end of the iteration, you won't see the chart burdown to zero.

In 1.0, we stored the burdown data in a format that made it impossible to see the zeros (since to save space, we did not store the zeros). That problem has been fixed in 2.0.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Mar 24 '09, 10:19 a.m.

Question was seen: 6,636 times

Last updated: Mar 24 '09, 10:19 a.m.

Confirmation Cancel Confirm