Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

RQM: Test Case work flow - Do not assign test cases with status draft to test plan - Possible?

Is it possible to define in RQM that a test case can not be assigned to a test plan, if the status of the test case is "draft"?

 thanks, joerg

0 votes


Accepted answer

Permanent link
Hi  Joerg,

I don't see any existing precondition that does what you are looking for. Here's more information on how you can configure various preconditions for  RQM test artifacts.
Jörg Werner selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers