Set two Iterations as "Current" under one Timeline


Bin Yang (725) | asked Jan 16 '14, 11:57 a.m.
Hello

Is that possible to set  multiple Iterations as "Current" under one Timeline?

I have multiple teams areas, and also multiple sub-team areas.  Each sub-team wants it's own Iteration.

Thanks.

Bin Yang.

Accepted answer


permanent link
Stephanie Bagot (2.1k1513) | answered Jan 16 '14, 12:56 p.m.
FORUM MODERATOR / JAZZ DEVELOPER
You can't have multiple current iterations as current under one timeline.
However, if your project area has multiple timelines, you can set one iteration as current in each timeline.
You can then configure the team area to work in the alternative timeline allowing each team area to have its own timeline and current iteration.
Bin Yang selected this answer as the correct answer