Hello

Is that possible to set  multiple Iterations as "Current" under one Timeline?

I have multiple teams areas, and also multiple sub-team areas.  Each sub-team wants it's own Iteration.

Thanks.

Bin Yang.

0 votes


Accepted answer

Permanent link
You can't have multiple current iterations as current under one timeline.
However, if your project area has multiple timelines, you can set one iteration as current in each timeline.
You can then configure the team area to work in the alternative timeline allowing each team area to have its own timeline and current iteration.
Bin Yang selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,136

Question asked: Jan 16 '14, 11:57 a.m.

Question was seen: 2,840 times

Last updated: Jan 16 '14, 12:56 p.m.

Confirmation Cancel Confirm