How do we set a particular order for the workitems in a Plan View?

We create a Work Breakdown Structure (WBS), which are a set of workitems in a parent child relationship. We set the order of the workitems the order of work. Now when I refresh the plan, the order gets jumbled up. How can I make sure this order is always maintained. This was a known issue in V2.0 but I am seeing the same in V4.0.2. 
Someone please let me know the fix for this. Thanks.

0 votes



One answer

Permanent link
The Sorting options for the Work Breakdown view are: Estimate, Planned Time, Priority, Ranking and User Defined (at least in the Scrum template). When you say "order of work", to which one are you referring? You might try changing the Sorting to "User Defined" which should remember your ordering. Other than that, on every refresh it should honor the configured sorting option.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,101

Question asked: Dec 19 '13, 5:57 a.m.

Question was seen: 5,226 times

Last updated: Dec 31 '13, 3:28 p.m.

Confirmation Cancel Confirm